Given an AOE network as follows:(5 points)

(a)What is the least amount of time in which the project may be complete ?

 


(b)Find the critical path(s) of the given AOE network.

V0-V2-V3-V4-V7-V8-V9

V0-V2-V3-V4-V5-V8-V9